Madrid-Segovia-Valladolid HSL New railway access to the north and northwest of Spain
España
13.486m de vía en placa
1viaducto
127.010m3 de hormigón armado
Execution of railway infrastructure and superstructure of the Soto del Real-Segovia section. High speed and single track 16,728 km long, of which, 13,396 km were constructed using a TBM 9.46 m in diameter. The project also included the construction of the Majalahita viaduct, with 16 spans and a total length of 702 m.
Basic units
941,623 m3 of tunnel excavation
127,010 m3 of reinforced concrete in segments, 17,341 m3 concrete in the tunnel floor
12,987 m2 of deck in the Majalahita viaduct
13,486 m of slab track
27,280 m of platforms and concrete sidewalks
Utilizamos cookies propias y de terceros para mejorar nuestros servicios y mostrarle publicidad relacionada con sus preferencias media. Puede cambiar la configuración u obtener más información en nuestra "Política de Cookies".
This website uses cookies to improve your experience while you navigate through the website. Out of these, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may affect your browsing experience.